The Cape construction progress

The registered completion date for The Cape is December 2028. At the last site inspection, in July 2026, it was 0.7% built. The developer is Barari Three Real Estate Development.

0.7%

Built, at the site inspection of 2 July 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
April 2102
Construction started
January 2026
First registered
January 2026
Developer
Barari Three Real Estate Development
Units
286
Escrow bank
National Bank of Ras Al Khaimah
Name in Arabic
ذا كيب
Project number
4258
Site inspections
2

Schedule

Between December 2025 and July 2026 the site added about 0.1 points a month. At that rate it would finish around April 2102, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

2 July 2026

0.7%+0.7 pts

  • The Cape construction site, inspection photo 1, 2 July 2026
  • The Cape construction site, inspection photo 2, 2 July 2026
  • The Cape construction site, inspection photo 3, 2 July 2026
  • The Cape construction site, inspection photo 4, 2 July 2026

16 December 2025

0%

  • The Cape construction site, inspection photo 1, 16 December 2025
  • The Cape construction site, inspection photo 2, 16 December 2025

All 7 site photos, by inspection date

Context

Own a unit in The Cape?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the The Cape handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2102. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on The Cape?
The Cape was 0.7% built at the site inspection on 2 July 2026. The site has been inspected 2 times since December 2025. The Land Department took 7 site photos at its inspections.
Is The Cape delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building The Cape?
The registered developer is Barari Three Real Estate Development.
Which bank holds the escrow account for The Cape?
National Bank of Ras Al Khaimah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.