Terva Homes construction progress

The registered completion date for Terva Homes is May 2027. At the last site inspection, in July 2026, it was 16% built. The developer is Rdg Property Development.

16%

Built, at the site inspection of 14 July 2026

Running behind its date

Registered completion date
May 2027
Finish at recent pace
March 2031
Construction started
October 2025
First registered
February 2026
Developer
Rdg Property Development
Units
24
Escrow bank
Bank of Baroda
Name in Arabic
تيرفا هومز
Project number
4231
Site inspections
2

Schedule

Between December 2025 and July 2026 the site added about 1.5 points a month. At that rate it would finish around March 2031, more than three months after its registered date of May 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

14 July 2026

16%+9.6 pts

  • Terva Homes construction site, inspection photo 1, 14 July 2026
  • Terva Homes construction site, inspection photo 2, 14 July 2026
  • Terva Homes construction site, inspection photo 3, 14 July 2026
  • Terva Homes construction site, inspection photo 4, 14 July 2026

31 December 2025

6.5%

  • Terva Homes construction site, inspection photo 1, 31 December 2025
  • Terva Homes construction site, inspection photo 2, 31 December 2025
  • Terva Homes construction site, inspection photo 3, 31 December 2025
  • Terva Homes construction site, inspection photo 4, 31 December 2025

All 12 site photos, by inspection date

Context

Own a unit in Terva Homes?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Terva Homes handover date?
The registered completion date is May 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2031. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Terva Homes?
Terva Homes was 16% built at the site inspection on 14 July 2026. The site has been inspected 2 times since December 2025. The Land Department took 12 site photos at its inspections.
Is Terva Homes delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
Who is building Terva Homes?
The registered developer is Rdg Property Development.
Which bank holds the escrow account for Terva Homes?
Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.