Terva Homes construction progress

Terva Homes is 16% built at the Land Department inspection of July 2026. Developer Rdg Property Development. Completion registered for May 2027.

16%

Built, at the Land Department site inspection of 14 July 2026

Running behind its date

Completion date (Land Department)
May 2027
Finish at recent pace
March 2031
Construction started
October 2025
Registered with the Land Department
February 2026
Developer
Rdg Property Development
Units
24
Escrow bank
Bank of Baroda
Name in Arabic
تيرفا هومز
Land Department project number
4231
Land Department site inspections
2

Schedule

Between December 2025 and July 2026 the site added about 1.5 points a month. At that rate it would finish around March 2031, more than three months after the May 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

14 July 2026

16%+9.6 pts

  • Terva Homes construction site, Land Department inspection photo 1, 14 July 2026
  • Terva Homes construction site, Land Department inspection photo 2, 14 July 2026
  • Terva Homes construction site, Land Department inspection photo 3, 14 July 2026
  • Terva Homes construction site, Land Department inspection photo 4, 14 July 2026

31 December 2025

6.5%

  • Terva Homes construction site, Land Department inspection photo 1, 31 December 2025
  • Terva Homes construction site, Land Department inspection photo 2, 31 December 2025
  • Terva Homes construction site, Land Department inspection photo 3, 31 December 2025
  • Terva Homes construction site, Land Department inspection photo 4, 31 December 2025

All 12 site photos, by inspection date

Context

Own a unit in Terva Homes?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Terva Homes be completed?
The completion date registered with the Dubai Land Department is May 2027. At the pace of its recent inspections the site would reach 100% around March 2031. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Terva Homes is built?
16%, measured at the Land Department site inspection on 14 July 2026. The Land Department engineers have inspected the site 2 times since December 2025.
Is Terva Homes delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2027.
Who is building Terva Homes?
The registered developer is Rdg Property Development.
Which bank holds the escrow account for Terva Homes?
Bank of Baroda. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.