Sunvale construction progress
Sunvale is 1.3% built at the Land Department inspection of June 2026. Developer Prysm Real Estate Development. Completion registered for May 2028.
1.3%
Built, at the Land Department site inspection of 23 June 2026
Running behind its date
- Completion date (Land Department)
- May 2028
- Finish at recent pace
- April 2072
- Construction started
- February 2026
- Registered with the Land Department
- November 2025
- Developer
- Prysm Real Estate Development
- Units
- 94
- Escrow bank
- Mashreq Bank
- Name in Arabic
- سونفيل
- Land Department project number
- 4196
- Land Department site inspections
- 2
Schedule
Between November 2025 and June 2026 the site added about 0.2 points a month. At that rate it would finish around April 2072, more than three months after the May 2028 date registered with the Land Department.
Site inspections
23 June 2026
1.3%+1.3 pts
11 November 2025
0%
Context
Own a unit in Sunvale?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Sunvale be completed?
- The completion date registered with the Dubai Land Department is May 2028. At the pace of its recent inspections the site would reach 100% around April 2072. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Sunvale is built?
- 1.3%, measured at the Land Department site inspection on 23 June 2026. The Land Department engineers have inspected the site 2 times since November 2025.
- Is Sunvale delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of May 2028.
- Who is building Sunvale?
- The registered developer is Prysm Real Estate Development.
- Which bank holds the escrow account for Sunvale?
- Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Deyaar ParkNearby in . 0%, Due December 2012, passed.
- Varazze TowerNearby in . 92%, Due February 2024, passed.
- Niki Lauda TowerNearby in . 0.4%.
- Champions Tower2Nearby in . 78%, Due October 2017, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.