Skip to content

Soma Residences construction progress

The registered completion date for Soma Residences is September 2028. At the last site inspection, in July 2026, it was 0% built. The developer is Origami Development.

0%

Built, at the site inspection of 16 July 2026

Running behind its date

Registered completion date
September 2028
Construction started
August 2026
First registered
June 2026
Developer
Origami Development
Units
44
Escrow bank
Mcb Bank Limited ( )
Name in Arabic
سوما ريزيدنسز
Project number
4453
Site inspections
2

Schedule

0%25%50%75%100%20272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 July 2026

0%

  • Soma Residences construction site, inspection photo 1, 16 July 2026
  • Soma Residences construction site, inspection photo 2, 16 July 2026
  • Soma Residences construction site, inspection photo 3, 16 July 2026

15 April 2026

0%

  • Soma Residences construction site, inspection photo 1, 15 April 2026
  • Soma Residences construction site, inspection photo 2, 15 April 2026

All 5 site photos, by inspection date

Context

Own a unit in Soma Residences?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Soma Residences handover date?
The registered completion date is September 2028. Handover of units starts once construction is complete, on the developer's schedule. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Soma Residences?
Soma Residences was 0% built at the site inspection on 16 July 2026. The site has been inspected 2 times since April 2026. The Land Department took 5 site photos at its inspections.
Is Soma Residences delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of September 2028.
Who is building Soma Residences?
The registered developer is Origami Development.
Which bank holds the escrow account for Soma Residences?
Mcb Bank Limited ( ). Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.