Sky Harmony By Peace Homes construction progress

Sky Harmony By Peace Homes is 13% built at the Land Department inspection of September 2026. Developer Peace Homes International Development. Completion registered for January 2029.

13%

Built, at the Land Department site inspection of 10 September 2026

Running behind its date

Completion date (Land Department)
January 2029
Finish at recent pace
December 2032
Construction started
January 2026
Registered with the Land Department
February 2026
Developer
Peace Homes International Development
Units
197
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
سكاي هارموني باي بيس هومز
Land Department project number
4147
Land Department site inspections
2

Schedule

Between October 2025 and September 2026 the site added about 1.2 points a month. At that rate it would finish around December 2032, more than three months after the January 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

10 September 2026

13%+13 pts

  • Sky Harmony By Peace Homes construction site, Land Department inspection photo 1, 10 September 2026
  • Sky Harmony By Peace Homes construction site, Land Department inspection photo 2, 10 September 2026
  • Sky Harmony By Peace Homes construction site, Land Department inspection photo 3, 10 September 2026
  • Sky Harmony By Peace Homes construction site, Land Department inspection photo 4, 10 September 2026

14 October 2025

0%

  • Sky Harmony By Peace Homes construction site, Land Department inspection photo 1, 14 October 2025
  • Sky Harmony By Peace Homes construction site, Land Department inspection photo 2, 14 October 2025

All 6 site photos, by inspection date

Context

Own a unit in Sky Harmony By Peace Homes?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Sky Harmony By Peace Homes be completed?
The completion date registered with the Dubai Land Department is January 2029. At the pace of its recent inspections the site would reach 100% around December 2032. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Sky Harmony By Peace Homes is built?
13%, measured at the Land Department site inspection on 10 September 2026. The Land Department engineers have inspected the site 2 times since October 2025.
Is Sky Harmony By Peace Homes delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2029.
Who is building Sky Harmony By Peace Homes?
The registered developer is Peace Homes International Development.
Which bank holds the escrow account for Sky Harmony By Peace Homes?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.