Rabdan Square construction progress
The registered completion date for Rabdan Square is March 2028. At the last site inspection, in October 2026, it was 1.2% built. The developer is Rabdan Square Developments.
1.2%
Built, at the site inspection of 7 October 2026
Running behind its date
- Registered completion date
- March 2028
- Finish at recent pace
- December 2076
- Construction started
- March 2026
- First registered
- March 2026
- Developer
- Rabdan Square Developments
- Units
- 36
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- ربدان سكوير
- Project number
- 4401
- Site inspections
- 2
Schedule
Between February 2026 and October 2026 the site added about 0.2 points a month. At that rate it would finish around December 2076, more than three months after its registered date of March 2028.
Site inspections
7 October 2026
1.2%+1.2 pts
19 February 2026
0%
Context
Own a unit in Rabdan Square?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Rabdan Square handover date?
- The registered completion date is March 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2076. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Rabdan Square?
- Rabdan Square was 1.2% built at the site inspection on 7 October 2026. The site has been inspected 2 times since February 2026. The Land Department took 5 site photos at its inspections.
- Is Rabdan Square delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
- Who is building Rabdan Square?
- The registered developer is Rabdan Square Developments.
- Which bank holds the escrow account for Rabdan Square?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.