Skip to content

Rabdan Gardens construction progress

Rabdan Gardens is 0% built at the Land Department inspection of June 2026. Developer Rabdan Gardens Real Estate Developments. Completion registered for March 2028.

0%

Built, at the Land Department site inspection of 23 June 2026

Running behind its date

Completion date (Land Department)
March 2028
Finish at recent pace
May 4435
Construction started
March 2026
Registered with the Land Department
February 2026
Developer
Rabdan Gardens Real Estate Developments
Units
90
Escrow bank
Dubai Islamic Bank
Name in Arabic
ربدان جاردنز
Land Department project number
4314
Land Department site inspections
2

Schedule

Between December 2025 and June 2026 the site added about 0.0 points a month. At that rate it would finish around May 4435, more than three months after the March 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

23 June 2026

0%+0.0 pts

  • Rabdan Gardens construction site, Land Department inspection photo 1, 23 June 2026
  • Rabdan Gardens construction site, Land Department inspection photo 2, 23 June 2026
  • Rabdan Gardens construction site, Land Department inspection photo 3, 23 June 2026

29 December 2025

0%

  • Rabdan Gardens construction site, Land Department inspection photo 1, 29 December 2025
  • Rabdan Gardens construction site, Land Department inspection photo 2, 29 December 2025

All 5 site photos, by inspection date

Context

Own a unit in Rabdan Gardens?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Rabdan Gardens be completed?
The completion date registered with the Dubai Land Department is March 2028. At the pace of its recent inspections the site would reach 100% around May 4435. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Rabdan Gardens is built?
0%, measured at the Land Department site inspection on 23 June 2026. The Land Department engineers have inspected the site 2 times since December 2025.
Is Rabdan Gardens delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2028.
Who is building Rabdan Gardens?
The registered developer is Rabdan Gardens Real Estate Developments.
Which bank holds the escrow account for Rabdan Gardens?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.