R Home Mh construction progress

The registered completion date for R Home Mh is August 2029. At the last site inspection, in October 2026, it was 1.8% built. The developer is Bukadra Development.

1.8%

Built, at the site inspection of 21 October 2026

Running behind its date

Registered completion date
August 2029
Finish at recent pace
October 2078
Construction started
March 2026
First registered
November 2025
Developer
Bukadra Development
Units
190
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
ار هوم ام اتش
Project number
4214
Site inspections
2

Schedule

Between November 2025 and October 2026 the site added about 0.2 points a month. At that rate it would finish around October 2078, more than three months after its registered date of August 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

21 October 2026

1.8%+1.8 pts

  • R Home Mh construction site, inspection photo 1, 21 October 2026
  • R Home Mh construction site, inspection photo 2, 21 October 2026
  • R Home Mh construction site, inspection photo 3, 21 October 2026
  • R Home Mh construction site, inspection photo 4, 21 October 2026

11 November 2025

0%

  • R Home Mh construction site, inspection photo 1, 11 November 2025
  • R Home Mh construction site, inspection photo 2, 11 November 2025

All 7 site photos, by inspection date

Context

Own a unit in R Home Mh?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the R Home Mh handover date?
The registered completion date is August 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2078. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on R Home Mh?
R Home Mh was 1.8% built at the site inspection on 21 October 2026. The site has been inspected 2 times since November 2025. The Land Department took 7 site photos at its inspections.
Is R Home Mh delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2029.
Who is building R Home Mh?
The registered developer is Bukadra Development.
Which bank holds the escrow account for R Home Mh?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.