Noore construction progress

The registered completion date for Noore is June 2027. At the last site inspection, in July 2026, it was 16% built. The developer is Eight Square Developers.

16%

Built, at the site inspection of 8 July 2026

Running behind its date

Registered completion date
June 2027
Finish at recent pace
August 2030
Construction started
December 2024
First registered
January 2026
Developer
Eight Square Developers
Units
43
Escrow bank
The National Bank of Fujairah
Name in Arabic
نووري
Project number
4252
Site inspections
2

Schedule

Between January 2026 and July 2026 the site added about 1.7 points a month. At that rate it would finish around August 2030, more than three months after its registered date of June 2027.

0%25%50%75%100%202520262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

8 July 2026

16%+10 pts

  • Noore construction site, inspection photo 1, 8 July 2026
  • Noore construction site, inspection photo 2, 8 July 2026
  • Noore construction site, inspection photo 3, 8 July 2026
  • Noore construction site, inspection photo 4, 8 July 2026

5 January 2026

5.5%

  • Noore construction site, inspection photo 1, 5 January 2026
  • Noore construction site, inspection photo 2, 5 January 2026
  • Noore construction site, inspection photo 3, 5 January 2026
  • Noore construction site, inspection photo 4, 5 January 2026

All 10 site photos, by inspection date

Context

Own a unit in Noore?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Noore handover date?
The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Noore?
Noore was 16% built at the site inspection on 8 July 2026. The site has been inspected 2 times since January 2026. The Land Department took 10 site photos at its inspections.
Is Noore delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
Who is building Noore?
The registered developer is Eight Square Developers.
Which bank holds the escrow account for Noore?
The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.