Noore construction progress
The registered completion date for Noore is June 2027. At the last site inspection, in July 2026, it was 16% built. The developer is Eight Square Developers.
16%
Built, at the site inspection of 8 July 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- August 2030
- Construction started
- December 2024
- First registered
- January 2026
- Developer
- Eight Square Developers
- Units
- 43
- Escrow bank
- The National Bank of Fujairah
- Name in Arabic
- نووري
- Project number
- 4252
- Site inspections
- 2
Schedule
Between January 2026 and July 2026 the site added about 1.7 points a month. At that rate it would finish around August 2030, more than three months after its registered date of June 2027.
Site inspections
8 July 2026
16%+10 pts
5 January 2026
5.5%
Context
Own a unit in Noore?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Noore handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2030. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Noore?
- Noore was 16% built at the site inspection on 8 July 2026. The site has been inspected 2 times since January 2026. The Land Department took 10 site photos at its inspections.
- Is Noore delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Noore?
- The registered developer is Eight Square Developers.
- Which bank holds the escrow account for Noore?
- The National Bank of Fujairah. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.