Niki Lauda Tower construction progress
Niki Lauda Tower was registered to complete in March 2026 and is still under construction. At the last site inspection, in July 2026, it was 0.4% built. The developer is Plt Properties Fzco.
0.4%
Built, at the site inspection of 27 July 2026
8 months past its registered completion date
- Registered completion date
- March 2026
- Finish at recent pace
- August 2188
- Construction started
- March 2023
- First registered
- March 2023
- Developer
- Plt Properties Fzco
- Units
- 384
- Escrow bank
- First Abu Dhabi Bank
- Name in Arabic
- برج نيكي لودا
- Project number
- 287
- Site inspections
- 3
Schedule
Niki Lauda Tower was registered to complete in March 2026, 8 months ago, and is still under construction. Over the last year of inspections it has added about 0.1 points a month. Kept at that rate, the site would reach 100% around August 2188.
Site inspections
27 July 2026
0.4%+0.2 pts
20 April 2026
0.3%+0.2 pts
25 December 2025
0.1%
Context
Own a unit in Niki Lauda Tower?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Niki Lauda Tower handover date?
- The registered completion date was March 2026, and the register still lists Niki Lauda Tower as under construction. At the pace of its recent inspections the site would reach 100% around August 2188. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Niki Lauda Tower?
- Niki Lauda Tower was 0.4% built at the site inspection on 27 July 2026. The site has been inspected 3 times since December 2025. The Land Department took 13 site photos at its inspections.
- Is Niki Lauda Tower delayed?
- Yes. Its registered completion date of March 2026 has passed and the project is still listed as under construction.
- Who is building Niki Lauda Tower?
- The registered developer is Plt Properties Fzco.
- Which bank holds the escrow account for Niki Lauda Tower?
- First Abu Dhabi Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.