Nanma Lotus construction progress
The registered completion date for Nanma Lotus is February 2028. At the last site inspection, in October 2026, it was 3.6% built. The developer is Nanma Properties.
3.6%
Built, at the site inspection of 15 October 2026
Running behind its date
- Registered completion date
- February 2028
- Finish at recent pace
- May 2040
- Construction started
- April 2026
- First registered
- May 2026
- Developer
- Nanma Properties
- Units
- 79
- Escrow bank
- Emirates NBD
- Name in Arabic
- نانما لوتس
- Project number
- 4447
- Site inspections
- 2
Schedule
Between April 2026 and October 2026 the site added about 0.6 points a month. At that rate it would finish around May 2040, more than three months after its registered date of February 2028.
Site inspections
15 October 2026
3.6%+3.6 pts
14 April 2026
0%
Context
Own a unit in Nanma Lotus?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Nanma Lotus handover date?
- The registered completion date is February 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around May 2040. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Nanma Lotus?
- Nanma Lotus was 3.6% built at the site inspection on 15 October 2026. The site has been inspected 2 times since April 2026. The Land Department took 6 site photos at its inspections.
- Is Nanma Lotus delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of February 2028.
- Who is building Nanma Lotus?
- The registered developer is Nanma Properties.
- Which bank holds the escrow account for Nanma Lotus?
- Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.