Mirdad construction progress
The registered completion date for Mirdad is December 2028. At the last site inspection, in September 2026, it was 6.0% built. The developer is Mirdad Real Estate Development.
6.0%
Built, at the site inspection of 28 September 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- November 2041
- Construction started
- August 2025
- First registered
- October 2025
- Developer
- Mirdad Real Estate Development
- Units
- 1,114
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- مرداد
- Project number
- 4158
- Site inspections
- 3
Schedule
Between October 2025 and September 2026 the site added about 0.5 points a month. At that rate it would finish around November 2041, more than three months after its registered date of December 2028.
Site inspections
28 September 2026
6.0%+3.2 pts
19 June 2026
2.8%+2.6 pts
24 October 2025
0.3%
Context
Own a unit in Mirdad?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Mirdad handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 2041. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Mirdad?
- Mirdad was 6.0% built at the site inspection on 28 September 2026. The site has been inspected 3 times since October 2025. The Land Department took 13 site photos at its inspections.
- Is Mirdad delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Mirdad?
- The registered developer is Mirdad Real Estate Development.
- Which bank holds the escrow account for Mirdad?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.