Lunaya construction progress
The registered completion date for Lunaya is March 2029. At the last site inspection, in November 2026, it was 4.1% built. The developer is Lunaya Zaya Real Estate Development S.o.c.
4.1%
Built, at the site inspection of 9 November 2026
Running behind its date
- Registered completion date
- March 2029
- Finish at recent pace
- February 2043
- Construction started
- April 2026
- First registered
- April 2026
- Developer
- Lunaya Zaya Real Estate Development S.o.c
- Units
- 910
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- لونايا
- Project number
- 4456
- Site inspections
- 3
Schedule
Between April 2026 and November 2026 the site added about 0.5 points a month. At that rate it would finish around February 2043, more than three months after its registered date of March 2029.
Site inspections
9 November 2026
4.1%+2.7 pts
30 June 2026
1.3%+0.7 pts
9 April 2026
0.6%
Context
Own a unit in Lunaya?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Lunaya handover date?
- The registered completion date is March 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2043. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Lunaya?
- Lunaya was 4.1% built at the site inspection on 9 November 2026. The site has been inspected 3 times since April 2026. The Land Department took 20 site photos at its inspections.
- Is Lunaya delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2029.
- Who is building Lunaya?
- The registered developer is Lunaya Zaya Real Estate Development S.o.c.
- Which bank holds the escrow account for Lunaya?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.