Lunaya construction progress

Lunaya is 1.3% built at the Land Department inspection of June 2026. Developer Lunaya Zaya Real Estate Development S.o.c. Completion registered for March 2029.

1.3%

Built, at the Land Department site inspection of 30 June 2026

Running behind its date

Completion date (Land Department)
March 2029
Finish at recent pace
February 2058
Construction started
April 2026
Registered with the Land Department
April 2026
Developer
Lunaya Zaya Real Estate Development S.o.c
Units
564
Escrow bank
Commercial Bank of Dubai
Name in Arabic
لونايا
Land Department project number
4456
Land Department site inspections
2

Schedule

Between April 2026 and June 2026 the site added about 0.3 points a month. At that rate it would finish around February 2058, more than three months after the March 2029 date registered with the Land Department.

0%25%50%75%100%202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

30 June 2026

1.3%+0.7 pts

  • Lunaya construction site, Land Department inspection photo 1, 30 June 2026
  • Lunaya construction site, Land Department inspection photo 2, 30 June 2026
  • Lunaya construction site, Land Department inspection photo 3, 30 June 2026
  • Lunaya construction site, Land Department inspection photo 4, 30 June 2026

9 April 2026

0.6%

  • Lunaya construction site, Land Department inspection photo 1, 9 April 2026
  • Lunaya construction site, Land Department inspection photo 2, 9 April 2026
  • Lunaya construction site, Land Department inspection photo 3, 9 April 2026
  • Lunaya construction site, Land Department inspection photo 4, 9 April 2026

All 10 site photos, by inspection date

Context

Own a unit in Lunaya?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Lunaya be completed?
The completion date registered with the Dubai Land Department is March 2029. At the pace of its recent inspections the site would reach 100% around February 2058. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Lunaya is built?
1.3%, measured at the Land Department site inspection on 30 June 2026. The Land Department engineers have inspected the site 2 times since April 2026.
Is Lunaya delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2029.
Who is building Lunaya?
The registered developer is Lunaya Zaya Real Estate Development S.o.c.
Which bank holds the escrow account for Lunaya?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.