Lunaya construction progress

The registered completion date for Lunaya is March 2029. At the last site inspection, in November 2026, it was 4.1% built. The developer is Lunaya Zaya Real Estate Development S.o.c.

4.1%

Built, at the site inspection of 9 November 2026

Running behind its date

Registered completion date
March 2029
Finish at recent pace
February 2043
Construction started
April 2026
First registered
April 2026
Developer
Lunaya Zaya Real Estate Development S.o.c
Units
910
Escrow bank
Commercial Bank of Dubai
Name in Arabic
لونايا
Project number
4456
Site inspections
3

Schedule

Between April 2026 and November 2026 the site added about 0.5 points a month. At that rate it would finish around February 2043, more than three months after its registered date of March 2029.

0%25%50%75%100%202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

9 November 2026

4.1%+2.7 pts

  • Lunaya construction site, inspection photo 1, 9 November 2026
  • Lunaya construction site, inspection photo 2, 9 November 2026
  • Lunaya construction site, inspection photo 3, 9 November 2026
  • Lunaya construction site, inspection photo 4, 9 November 2026

30 June 2026

1.3%+0.7 pts

  • Lunaya construction site, inspection photo 1, 30 June 2026
  • Lunaya construction site, inspection photo 2, 30 June 2026
  • Lunaya construction site, inspection photo 3, 30 June 2026
  • Lunaya construction site, inspection photo 4, 30 June 2026

9 April 2026

0.6%

  • Lunaya construction site, inspection photo 1, 9 April 2026
  • Lunaya construction site, inspection photo 2, 9 April 2026
  • Lunaya construction site, inspection photo 3, 9 April 2026
  • Lunaya construction site, inspection photo 4, 9 April 2026

All 20 site photos, by inspection date

Context

Own a unit in Lunaya?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Lunaya handover date?
The registered completion date is March 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2043. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Lunaya?
Lunaya was 4.1% built at the site inspection on 9 November 2026. The site has been inspected 3 times since April 2026. The Land Department took 20 site photos at its inspections.
Is Lunaya delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2029.
Who is building Lunaya?
The registered developer is Lunaya Zaya Real Estate Development S.o.c.
Which bank holds the escrow account for Lunaya?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.