Longfor International Center construction progress
The registered completion date for Longfor International Center is December 2027. At the last site inspection, in October 2026, it was 1.6% built. The developer is Star Lang Real Estate Development.
1.6%
Built, at the site inspection of 15 October 2026
Running behind its date
- Registered completion date
- December 2027
- Finish at recent pace
- April 2062
- Construction started
- May 2026
- First registered
- April 2026
- Developer
- Star Lang Real Estate Development
- Units
- 72
- Escrow bank
- United Bank Limited
- Name in Arabic
- مركز لونجفور الدولي
- Project number
- 4439
- Site inspections
- 2
Schedule
Between March 2026 and October 2026 the site added about 0.2 points a month. At that rate it would finish around April 2062, more than three months after its registered date of December 2027.
Site inspections
15 October 2026
1.6%+1.6 pts
13 March 2026
0%
Context
Own a unit in Longfor International Center?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Longfor International Center handover date?
- The registered completion date is December 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2062. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Longfor International Center?
- Longfor International Center was 1.6% built at the site inspection on 15 October 2026. The site has been inspected 2 times since March 2026. The Land Department took 4 site photos at its inspections.
- Is Longfor International Center delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2027.
- Who is building Longfor International Center?
- The registered developer is Star Lang Real Estate Development.
- Which bank holds the escrow account for Longfor International Center?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.