Liv Oceanside construction progress

Liv Oceanside is 7.4% built at the Land Department inspection of June 2026. Developer Liv Island Real Estate Development. Completion registered for November 2027.

7.4%

Built, at the Land Department site inspection of 18 June 2026

Running behind its date

Completion date (Land Department)
November 2027
Finish at recent pace
March 2075
Construction started
October 2025
Registered with the Land Department
November 2025
Developer
Liv Island Real Estate Development
Units
118
Escrow bank
Dubai Islamic Bank
Name in Arabic
ليف أوشنسايد
Land Department project number
4191
Land Department site inspections
2

Schedule

Between November 2025 and June 2026 the site added about 0.2 points a month. At that rate it would finish around March 2075, more than three months after the November 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

18 June 2026

7.4%+1.2 pts

  • Liv Oceanside construction site, Land Department inspection photo 1, 18 June 2026
  • Liv Oceanside construction site, Land Department inspection photo 2, 18 June 2026
  • Liv Oceanside construction site, Land Department inspection photo 3, 18 June 2026

7 November 2025

6.3%

  • Liv Oceanside construction site, Land Department inspection photo 1, 7 November 2025
  • Liv Oceanside construction site, Land Department inspection photo 2, 7 November 2025
  • Liv Oceanside construction site, Land Department inspection photo 3, 7 November 2025
  • Liv Oceanside construction site, Land Department inspection photo 4, 7 November 2025

All 7 site photos, by inspection date

Context

Own a unit in Liv Oceanside?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Liv Oceanside be completed?
The completion date registered with the Dubai Land Department is November 2027. At the pace of its recent inspections the site would reach 100% around March 2075. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Liv Oceanside is built?
7.4%, measured at the Land Department site inspection on 18 June 2026. The Land Department engineers have inspected the site 2 times since November 2025.
Is Liv Oceanside delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Liv Oceanside?
The registered developer is Liv Island Real Estate Development.
Which bank holds the escrow account for Liv Oceanside?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.