Liv Oceanside construction progress
Liv Oceanside is 7.4% built at the Land Department inspection of June 2026. Developer Liv Island Real Estate Development. Completion registered for November 2027.
7.4%
Built, at the Land Department site inspection of 18 June 2026
Running behind its date
- Completion date (Land Department)
- November 2027
- Finish at recent pace
- March 2075
- Construction started
- October 2025
- Registered with the Land Department
- November 2025
- Developer
- Liv Island Real Estate Development
- Units
- 118
- Escrow bank
- Dubai Islamic Bank
- Name in Arabic
- ليف أوشنسايد
- Land Department project number
- 4191
- Land Department site inspections
- 2
Schedule
Between November 2025 and June 2026 the site added about 0.2 points a month. At that rate it would finish around March 2075, more than three months after the November 2027 date registered with the Land Department.
Site inspections
18 June 2026
7.4%+1.2 pts
7 November 2025
6.3%
Context
Own a unit in Liv Oceanside?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Liv Oceanside be completed?
- The completion date registered with the Dubai Land Department is November 2027. At the pace of its recent inspections the site would reach 100% around March 2075. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Liv Oceanside is built?
- 7.4%, measured at the Land Department site inspection on 18 June 2026. The Land Department engineers have inspected the site 2 times since November 2025.
- Is Liv Oceanside delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
- Who is building Liv Oceanside?
- The registered developer is Liv Island Real Estate Development.
- Which bank holds the escrow account for Liv Oceanside?
- Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.