Liv Oceanside construction progress

The registered completion date for Liv Oceanside is November 2027. At the last site inspection, in October 2026, it was 14% built. The developer is Liv Island Real Estate Development.

14%

Built, at the site inspection of 22 October 2026

Running behind its date

Registered completion date
November 2027
Finish at recent pace
March 2037
Construction started
October 2025
First registered
November 2025
Developer
Liv Island Real Estate Development
Units
118
Escrow bank
Dubai Islamic Bank
Name in Arabic
ليف أوشنسايد
Project number
4191
Site inspections
3

Schedule

Between November 2025 and October 2026 the site added about 0.7 points a month. At that rate it would finish around March 2037, more than three months after its registered date of November 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 October 2026

14%+6.7 pts

  • Liv Oceanside construction site, inspection photo 1, 22 October 2026
  • Liv Oceanside construction site, inspection photo 2, 22 October 2026
  • Liv Oceanside construction site, inspection photo 3, 22 October 2026
  • Liv Oceanside construction site, inspection photo 4, 22 October 2026

18 June 2026

7.4%+1.2 pts

  • Liv Oceanside construction site, inspection photo 1, 18 June 2026
  • Liv Oceanside construction site, inspection photo 2, 18 June 2026
  • Liv Oceanside construction site, inspection photo 3, 18 June 2026

7 November 2025

6.3%

  • Liv Oceanside construction site, inspection photo 1, 7 November 2025
  • Liv Oceanside construction site, inspection photo 2, 7 November 2025
  • Liv Oceanside construction site, inspection photo 3, 7 November 2025
  • Liv Oceanside construction site, inspection photo 4, 7 November 2025

All 14 site photos, by inspection date

Context

Own a unit in Liv Oceanside?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Liv Oceanside handover date?
The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around March 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Liv Oceanside?
Liv Oceanside was 14% built at the site inspection on 22 October 2026. The site has been inspected 3 times since November 2025. The Land Department took 14 site photos at its inspections.
Is Liv Oceanside delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of November 2027.
Who is building Liv Oceanside?
The registered developer is Liv Island Real Estate Development.
Which bank holds the escrow account for Liv Oceanside?
Dubai Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.