Khk 31 construction progress

Khk 31 is 26% built at the Land Department inspection of August 2026. Developer Khk Realestate Development. Completion registered for March 2027.

26%

Built, at the Land Department site inspection of 31 August 2026

Running behind its date

Completion date (Land Department)
March 2027
Finish at recent pace
October 2028
Construction started
September 2025
Registered with the Land Department
December 2025
Developer
Khk Realestate Development
Units
160
Escrow bank
Sharjah Islamic Bank
Name in Arabic
كيه أتش كيه 31
Land Department project number
4153
Land Department site inspections
3

Schedule

Between December 2025 and August 2026 the site added about 2.9 points a month. At that rate it would finish around October 2028, more than three months after the March 2027 date registered with the Land Department.

0%25%50%75%100%20262027
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

31 August 2026

26%+12 pts

  • Khk 31 construction site, Land Department inspection photo 1, 31 August 2026
  • Khk 31 construction site, Land Department inspection photo 2, 31 August 2026
  • Khk 31 construction site, Land Department inspection photo 3, 31 August 2026
  • Khk 31 construction site, Land Department inspection photo 4, 31 August 2026

12 May 2026

14%+14 pts

  • Khk 31 construction site, Land Department inspection photo 1, 12 May 2026
  • Khk 31 construction site, Land Department inspection photo 2, 12 May 2026
  • Khk 31 construction site, Land Department inspection photo 3, 12 May 2026
  • Khk 31 construction site, Land Department inspection photo 4, 12 May 2026

3 December 2025

0%

  • Khk 31 construction site, Land Department inspection photo 1, 3 December 2025
  • Khk 31 construction site, Land Department inspection photo 2, 3 December 2025
  • Khk 31 construction site, Land Department inspection photo 3, 3 December 2025

All 14 site photos, by inspection date

Context

Own a unit in Khk 31?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Khk 31 be completed?
The completion date registered with the Dubai Land Department is March 2027. At the pace of its recent inspections the site would reach 100% around October 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Khk 31 is built?
26%, measured at the Land Department site inspection on 31 August 2026. The Land Department engineers have inspected the site 3 times since December 2025.
Is Khk 31 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Khk 31?
The registered developer is Khk Realestate Development.
Which bank holds the escrow account for Khk 31?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.