Khk 31 construction progress

The registered completion date for Khk 31 is March 2027. At the last site inspection, in August 2026, it was 26% built. The developer is Khk Realestate Development.

26%

Built, at the site inspection of 31 August 2026

Running behind its date

Registered completion date
March 2027
Finish at recent pace
October 2028
Construction started
September 2025
First registered
December 2025
Developer
Khk Realestate Development
Units
160
Escrow bank
Sharjah Islamic Bank
Name in Arabic
كيه أتش كيه 31
Project number
4153
Site inspections
3

Schedule

Between December 2025 and August 2026 the site added about 2.9 points a month. At that rate it would finish around October 2028, more than three months after its registered date of March 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

31 August 2026

26%+12 pts

  • Khk 31 construction site, inspection photo 1, 31 August 2026
  • Khk 31 construction site, inspection photo 2, 31 August 2026
  • Khk 31 construction site, inspection photo 3, 31 August 2026
  • Khk 31 construction site, inspection photo 4, 31 August 2026

12 May 2026

14%+14 pts

  • Khk 31 construction site, inspection photo 1, 12 May 2026
  • Khk 31 construction site, inspection photo 2, 12 May 2026
  • Khk 31 construction site, inspection photo 3, 12 May 2026
  • Khk 31 construction site, inspection photo 4, 12 May 2026

3 December 2025

0%

  • Khk 31 construction site, inspection photo 1, 3 December 2025
  • Khk 31 construction site, inspection photo 2, 3 December 2025
  • Khk 31 construction site, inspection photo 3, 3 December 2025

All 14 site photos, by inspection date

Context

Own a unit in Khk 31?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Khk 31 handover date?
The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Khk 31?
Khk 31 was 26% built at the site inspection on 31 August 2026. The site has been inspected 3 times since December 2025. The Land Department took 14 site photos at its inspections.
Is Khk 31 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
Who is building Khk 31?
The registered developer is Khk Realestate Development.
Which bank holds the escrow account for Khk 31?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.