Khk 31 construction progress
The registered completion date for Khk 31 is March 2027. At the last site inspection, in August 2026, it was 26% built. The developer is Khk Realestate Development.
26%
Built, at the site inspection of 31 August 2026
Running behind its date
- Registered completion date
- March 2027
- Finish at recent pace
- October 2028
- Construction started
- September 2025
- First registered
- December 2025
- Developer
- Khk Realestate Development
- Units
- 160
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- كيه أتش كيه 31
- Project number
- 4153
- Site inspections
- 3
Schedule
Between December 2025 and August 2026 the site added about 2.9 points a month. At that rate it would finish around October 2028, more than three months after its registered date of March 2027.
Site inspections
31 August 2026
26%+12 pts
12 May 2026
14%+14 pts
3 December 2025
0%
Context
Own a unit in Khk 31?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Khk 31 handover date?
- The registered completion date is March 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Khk 31?
- Khk 31 was 26% built at the site inspection on 31 August 2026. The site has been inspected 3 times since December 2025. The Land Department took 14 site photos at its inspections.
- Is Khk 31 delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2027.
- Who is building Khk 31?
- The registered developer is Khk Realestate Development.
- Which bank holds the escrow account for Khk 31?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.