Skip to content

Imtiaz Symphony Tower construction progress

The registered completion date for Imtiaz Symphony Tower is June 2029. At the last site inspection, in September 2026, it was 6.3% built. The developer is Imtiaz Symphony Development.

6.3%

Built, at the site inspection of 16 September 2026

Running behind its date

Registered completion date
June 2029
Finish at recent pace
July 2039
Construction started
December 2025
First registered
November 2025
Developer
Imtiaz Symphony Development
Units
369
Escrow bank
United Bank Limited
Name in Arabic
امتيازسيمفوني تاور
Project number
4193
Site inspections
4

Schedule

Between November 2025 and September 2026 the site added about 0.6 points a month. At that rate it would finish around July 2039, more than three months after its registered date of June 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

16 September 2026

6.3%+2.3 pts

  • Imtiaz Symphony Tower construction site, inspection photo 1, 16 September 2026
  • Imtiaz Symphony Tower construction site, inspection photo 2, 16 September 2026
  • Imtiaz Symphony Tower construction site, inspection photo 3, 16 September 2026
  • Imtiaz Symphony Tower construction site, inspection photo 4, 16 September 2026

16 June 2026

4.0%+2.8 pts

  • Imtiaz Symphony Tower construction site, inspection photo 1, 16 June 2026
  • Imtiaz Symphony Tower construction site, inspection photo 2, 16 June 2026
  • Imtiaz Symphony Tower construction site, inspection photo 3, 16 June 2026
  • Imtiaz Symphony Tower construction site, inspection photo 4, 16 June 2026

26 March 2026

1.2%+1.2 pts

  • Imtiaz Symphony Tower construction site, inspection photo 1, 26 March 2026
  • Imtiaz Symphony Tower construction site, inspection photo 2, 26 March 2026
  • Imtiaz Symphony Tower construction site, inspection photo 3, 26 March 2026
  • Imtiaz Symphony Tower construction site, inspection photo 4, 26 March 2026

5 November 2025

0%

  • Imtiaz Symphony Tower construction site, inspection photo 1, 5 November 2025
  • Imtiaz Symphony Tower construction site, inspection photo 2, 5 November 2025
  • Imtiaz Symphony Tower construction site, inspection photo 3, 5 November 2025
  • Imtiaz Symphony Tower construction site, inspection photo 4, 5 November 2025

All 18 site photos, by inspection date

Context

Own a unit in Imtiaz Symphony Tower?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Imtiaz Symphony Tower handover date?
The registered completion date is June 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around July 2039. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Imtiaz Symphony Tower?
Imtiaz Symphony Tower was 6.3% built at the site inspection on 16 September 2026. The site has been inspected 4 times since November 2025. The Land Department took 18 site photos at its inspections.
Is Imtiaz Symphony Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
Who is building Imtiaz Symphony Tower?
The registered developer is Imtiaz Symphony Development.
Which bank holds the escrow account for Imtiaz Symphony Tower?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.