Imtiaz Symphony Tower construction progress

Imtiaz Symphony Tower is 6.3% built at the Land Department inspection of September 2026. Developer Imtiaz Symphony Development. Completion registered for June 2029.

6.3%

Built, at the Land Department site inspection of 16 September 2026

Running behind its date

Completion date (Land Department)
June 2029
Finish at recent pace
July 2039
Construction started
December 2025
Registered with the Land Department
November 2025
Developer
Imtiaz Symphony Development
Units
369
Escrow bank
United Bank Limited
Name in Arabic
امتيازسيمفوني تاور
Land Department project number
4193
Land Department site inspections
4

Schedule

Between November 2025 and September 2026 the site added about 0.6 points a month. At that rate it would finish around July 2039, more than three months after the June 2029 date registered with the Land Department.

0%25%50%75%100%2026202720282029
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

16 September 2026

6.3%+2.3 pts

  • Imtiaz Symphony Tower construction site, Land Department inspection photo 1, 16 September 2026
  • Imtiaz Symphony Tower construction site, Land Department inspection photo 2, 16 September 2026
  • Imtiaz Symphony Tower construction site, Land Department inspection photo 3, 16 September 2026
  • Imtiaz Symphony Tower construction site, Land Department inspection photo 4, 16 September 2026

16 June 2026

4.0%+2.8 pts

  • Imtiaz Symphony Tower construction site, Land Department inspection photo 1, 16 June 2026
  • Imtiaz Symphony Tower construction site, Land Department inspection photo 2, 16 June 2026
  • Imtiaz Symphony Tower construction site, Land Department inspection photo 3, 16 June 2026
  • Imtiaz Symphony Tower construction site, Land Department inspection photo 4, 16 June 2026

26 March 2026

1.2%+1.2 pts

  • Imtiaz Symphony Tower construction site, Land Department inspection photo 1, 26 March 2026
  • Imtiaz Symphony Tower construction site, Land Department inspection photo 2, 26 March 2026
  • Imtiaz Symphony Tower construction site, Land Department inspection photo 3, 26 March 2026
  • Imtiaz Symphony Tower construction site, Land Department inspection photo 4, 26 March 2026

5 November 2025

0%

  • Imtiaz Symphony Tower construction site, Land Department inspection photo 1, 5 November 2025
  • Imtiaz Symphony Tower construction site, Land Department inspection photo 2, 5 November 2025
  • Imtiaz Symphony Tower construction site, Land Department inspection photo 3, 5 November 2025
  • Imtiaz Symphony Tower construction site, Land Department inspection photo 4, 5 November 2025

All 18 site photos, by inspection date

Context

Own a unit in Imtiaz Symphony Tower?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Track the handover

Questions

When will Imtiaz Symphony Tower be completed?
The completion date registered with the Dubai Land Department is June 2029. At the pace of its recent inspections the site would reach 100% around July 2039. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Imtiaz Symphony Tower is built?
6.3%, measured at the Land Department site inspection on 16 September 2026. The Land Department engineers have inspected the site 4 times since November 2025.
Is Imtiaz Symphony Tower delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
Who is building Imtiaz Symphony Tower?
The registered developer is Imtiaz Symphony Development.
Which bank holds the escrow account for Imtiaz Symphony Tower?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.