Imtiaz Symphony Tower construction progress
Imtiaz Symphony Tower is 6.3% built at the Land Department inspection of September 2026. Developer Imtiaz Symphony Development. Completion registered for June 2029.
6.3%
Built, at the Land Department site inspection of 16 September 2026
Running behind its date
- Completion date (Land Department)
- June 2029
- Finish at recent pace
- July 2039
- Construction started
- December 2025
- Registered with the Land Department
- November 2025
- Developer
- Imtiaz Symphony Development
- Units
- 369
- Escrow bank
- United Bank Limited
- Name in Arabic
- امتيازسيمفوني تاور
- Land Department project number
- 4193
- Land Department site inspections
- 4
Schedule
Between November 2025 and September 2026 the site added about 0.6 points a month. At that rate it would finish around July 2039, more than three months after the June 2029 date registered with the Land Department.
Site inspections
16 September 2026
6.3%+2.3 pts
16 June 2026
4.0%+2.8 pts
26 March 2026
1.2%+1.2 pts
5 November 2025
0%
Context
Own a unit in Imtiaz Symphony Tower?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Track the handoverQuestions
- When will Imtiaz Symphony Tower be completed?
- The completion date registered with the Dubai Land Department is June 2029. At the pace of its recent inspections the site would reach 100% around July 2039. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Imtiaz Symphony Tower is built?
- 6.3%, measured at the Land Department site inspection on 16 September 2026. The Land Department engineers have inspected the site 4 times since November 2025.
- Is Imtiaz Symphony Tower delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2029.
- Who is building Imtiaz Symphony Tower?
- The registered developer is Imtiaz Symphony Development.
- Which bank holds the escrow account for Imtiaz Symphony Tower?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Deyaar ParkNearby in . 0%, Due December 2012, passed.
- Varazze TowerNearby in . 92%, Due February 2024, passed.
- Niki Lauda TowerNearby in . 0.4%.
- Champions Tower2Nearby in . 78%, Due October 2017, passed.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.