Hq By Rove construction progress

The registered completion date for Hq By Rove is March 2029. At the last site inspection, in July 2026, it was 0.7% built. The developer is Irth Urban Development.

0.7%

Built, at the site inspection of 6 July 2026

Running behind its date

Registered completion date
March 2029
Finish at recent pace
October 2131
Construction started
December 2025
First registered
October 2025
Developer
Irth Urban Development
Units
414
Escrow bank
Commercial Bank of Dubai
Name in Arabic
اتش كيو بواسطة روف
Project number
4143
Site inspections
3

Schedule

Between October 2025 and July 2026 the site added about 0.1 points a month. At that rate it would finish around October 2131, more than three months after its registered date of March 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

6 July 2026

0.7%+0.6 pts

  • Hq By Rove construction site, inspection photo 1, 6 July 2026
  • Hq By Rove construction site, inspection photo 2, 6 July 2026
  • Hq By Rove construction site, inspection photo 3, 6 July 2026
  • Hq By Rove construction site, inspection photo 4, 6 July 2026

23 March 2026

0.1%+0.1 pts

  • Hq By Rove construction site, inspection photo 1, 23 March 2026
  • Hq By Rove construction site, inspection photo 2, 23 March 2026
  • Hq By Rove construction site, inspection photo 3, 23 March 2026
  • Hq By Rove construction site, inspection photo 4, 23 March 2026

8 October 2025

0%

  • Hq By Rove construction site, inspection photo 1, 8 October 2025
  • Hq By Rove construction site, inspection photo 2, 8 October 2025

All 12 site photos, by inspection date

Context

Own a unit in Hq By Rove?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Hq By Rove handover date?
The registered completion date is March 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2131. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Hq By Rove?
Hq By Rove was 0.7% built at the site inspection on 6 July 2026. The site has been inspected 3 times since October 2025. The Land Department took 12 site photos at its inspections.
Is Hq By Rove delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2029.
Who is building Hq By Rove?
The registered developer is Irth Urban Development.
Which bank holds the escrow account for Hq By Rove?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.