Hq By Rove construction progress
Hq By Rove is 0.7% built at the Land Department inspection of July 2026. Developer Irth Urban Development. Completion registered for March 2029.
0.7%
Built, at the Land Department site inspection of 6 July 2026
Running behind its date
- Completion date (Land Department)
- March 2029
- Finish at recent pace
- October 2131
- Construction started
- December 2025
- Registered with the Land Department
- October 2025
- Developer
- Irth Urban Development
- Units
- 414
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- اتش كيو بواسطة روف
- Land Department project number
- 4143
- Land Department site inspections
- 3
Schedule
Between October 2025 and July 2026 the site added about 0.1 points a month. At that rate it would finish around October 2131, more than three months after the March 2029 date registered with the Land Department.
Site inspections
6 July 2026
0.7%+0.6 pts
23 March 2026
0.1%+0.1 pts
8 October 2025
0%
Context
Own a unit in Hq By Rove?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Hq By Rove be completed?
- The completion date registered with the Dubai Land Department is March 2029. At the pace of its recent inspections the site would reach 100% around October 2131. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Hq By Rove is built?
- 0.7%, measured at the Land Department site inspection on 6 July 2026. The Land Department engineers have inspected the site 3 times since October 2025.
- Is Hq By Rove delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of March 2029.
- Who is building Hq By Rove?
- The registered developer is Irth Urban Development.
- Which bank holds the escrow account for Hq By Rove?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.