Hermina By Casagrand Gallantee Real Estate construction progress

The registered completion date for Hermina By Casagrand Gallantee Real Estate is October 2029. At the last site inspection, in October 2026, it was 4.7% built. The developer is Casagrand Gallantee Real Estate.

4.7%

Built, at the site inspection of 20 October 2026

Running behind its date

Registered completion date
October 2029
Finish at recent pace
August 2037
Construction started
December 2025
First registered
November 2025
Developer
Casagrand Gallantee Real Estate
Units
135
Escrow bank
Emirates Islamic Bank
Name in Arabic
هيرمينا من كاساجراند جلانتي للعقارات ش
Project number
4152
Site inspections
3

Schedule

Between April 2026 and October 2026 the site added about 0.7 points a month. At that rate it would finish around August 2037, more than three months after its registered date of October 2029.

0%25%50%75%100%2026202720282029
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 October 2026

4.7%+4.2 pts

  • Hermina By Casagrand Gallantee Real Estate construction site, inspection photo 1, 20 October 2026
  • Hermina By Casagrand Gallantee Real Estate construction site, inspection photo 2, 20 October 2026
  • Hermina By Casagrand Gallantee Real Estate construction site, inspection photo 3, 20 October 2026
  • Hermina By Casagrand Gallantee Real Estate construction site, inspection photo 4, 20 October 2026

29 April 2026

0.5%+0.5 pts

  • Hermina By Casagrand Gallantee Real Estate construction site, inspection photo 1, 29 April 2026
  • Hermina By Casagrand Gallantee Real Estate construction site, inspection photo 2, 29 April 2026
  • Hermina By Casagrand Gallantee Real Estate construction site, inspection photo 3, 29 April 2026
  • Hermina By Casagrand Gallantee Real Estate construction site, inspection photo 4, 29 April 2026

16 October 2025

0%

  • Hermina By Casagrand Gallantee Real Estate construction site, inspection photo 1, 16 October 2025
  • Hermina By Casagrand Gallantee Real Estate construction site, inspection photo 2, 16 October 2025

All 13 site photos, by inspection date

Context

Own a unit in Hermina By Casagrand Gallantee Real Estate?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Hermina By Casagrand Gallantee Real Estate handover date?
The registered completion date is October 2029. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around August 2037. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Hermina By Casagrand Gallantee Real Estate?
Hermina By Casagrand Gallantee Real Estate was 4.7% built at the site inspection on 20 October 2026. The site has been inspected 3 times since October 2025. The Land Department took 13 site photos at its inspections.
Is Hermina By Casagrand Gallantee Real Estate delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of October 2029.
Who is building Hermina By Casagrand Gallantee Real Estate?
The registered developer is Casagrand Gallantee Real Estate.
Which bank holds the escrow account for Hermina By Casagrand Gallantee Real Estate?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.