Hearth Heights By Enawt Real Estate Development construction progress
Hearth Heights By Enawt Real Estate Development was registered to complete in October 2026 and is still under construction. At the last site inspection, in July 2026, it was 29% built. The developer is Enawt Real Estate Development.
29%
Built, at the site inspection of 6 July 2026
2 months past its registered completion date
- Registered completion date
- October 2026
- Finish at recent pace
- June 2029
- Construction started
- April 2025
- First registered
- January 2026
- Developer
- Enawt Real Estate Development
- Units
- 142
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- هارث هايتس - إناوت للتطوير العقاري
- Project number
- 4203
- Site inspections
- 2
Schedule
Hearth Heights By Enawt Real Estate Development was registered to complete in October 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 2.0 points a month. Kept at that rate, the site would reach 100% around June 2029.
Site inspections
6 July 2026
29%+13 pts
18 December 2025
16%
Context
Own a unit in Hearth Heights By Enawt Real Estate Development?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Hearth Heights By Enawt Real Estate Development handover date?
- The registered completion date was October 2026, and the register still lists Hearth Heights By Enawt Real Estate Development as under construction. At the pace of its recent inspections the site would reach 100% around June 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Hearth Heights By Enawt Real Estate Development?
- Hearth Heights By Enawt Real Estate Development was 29% built at the site inspection on 6 July 2026. The site has been inspected 2 times since December 2025. The Land Department took 16 site photos at its inspections.
- Is Hearth Heights By Enawt Real Estate Development delayed?
- Yes. Its registered completion date of October 2026 has passed and the project is still listed as under construction.
- Who is building Hearth Heights By Enawt Real Estate Development?
- The registered developer is Enawt Real Estate Development.
- Which bank holds the escrow account for Hearth Heights By Enawt Real Estate Development?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)

.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)
.jpeg&w=3840&q=75)