Enre Residence By Imtiaz construction progress

The registered completion date for Enre Residence By Imtiaz is August 2028. At the last site inspection, in October 2026, it was 24% built. The developer is Imtiaz South Real Estate Development.

24%

Built, at the site inspection of 30 October 2026

Running behind its date

Registered completion date
August 2028
Finish at recent pace
April 2029
Construction started
February 2026
First registered
February 2026
Developer
Imtiaz South Real Estate Development
Units
170
Escrow bank
United Bank Limited
Name in Arabic
إنري ريزيدنس من امتياز
Project number
4336
Site inspections
4

Schedule

Between January 2026 and October 2026 the site added about 2.6 points a month. At that rate it would finish around April 2029, more than three months after its registered date of August 2028.

0%25%50%75%100%20272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

30 October 2026

24%+9.6 pts

  • Enre Residence By Imtiaz construction site, inspection photo 1, 30 October 2026
  • Enre Residence By Imtiaz construction site, inspection photo 2, 30 October 2026
  • Enre Residence By Imtiaz construction site, inspection photo 3, 30 October 2026
  • Enre Residence By Imtiaz construction site, inspection photo 4, 30 October 2026

28 July 2026

15%+7.4 pts

  • Enre Residence By Imtiaz construction site, inspection photo 1, 28 July 2026
  • Enre Residence By Imtiaz construction site, inspection photo 2, 28 July 2026
  • Enre Residence By Imtiaz construction site, inspection photo 3, 28 July 2026
  • Enre Residence By Imtiaz construction site, inspection photo 4, 28 July 2026

27 April 2026

7.3%+7.3 pts

  • Enre Residence By Imtiaz construction site, inspection photo 1, 27 April 2026
  • Enre Residence By Imtiaz construction site, inspection photo 2, 27 April 2026
  • Enre Residence By Imtiaz construction site, inspection photo 3, 27 April 2026

16 January 2026

0%

  • Enre Residence By Imtiaz construction site, inspection photo 1, 16 January 2026
  • Enre Residence By Imtiaz construction site, inspection photo 2, 16 January 2026
  • Enre Residence By Imtiaz construction site, inspection photo 3, 16 January 2026

All 17 site photos, by inspection date

Context

Own a unit in Enre Residence By Imtiaz?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Enre Residence By Imtiaz handover date?
The registered completion date is August 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2029. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Enre Residence By Imtiaz?
Enre Residence By Imtiaz was 24% built at the site inspection on 30 October 2026. The site has been inspected 4 times since January 2026. The Land Department took 17 site photos at its inspections.
Is Enre Residence By Imtiaz delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of August 2028.
Who is building Enre Residence By Imtiaz?
The registered developer is Imtiaz South Real Estate Development.
Which bank holds the escrow account for Enre Residence By Imtiaz?
United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.