Enchante By Grid construction progress
The registered completion date for Enchante By Grid is December 2028. At the last site inspection, in November 2026, it was 1.6% built. The developer is Grid Viv Real Estate Development.
1.6%
Built, at the site inspection of 11 November 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- January 2061
- Construction started
- May 2026
- First registered
- April 2026
- Developer
- Grid Viv Real Estate Development
- Units
- 286
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- إنشانته باي جريد
- Project number
- 4460
- Site inspections
- 2
Schedule
Between April 2026 and November 2026 the site added about 0.2 points a month. At that rate it would finish around January 2061, more than three months after its registered date of December 2028.
Site inspections
11 November 2026
1.6%+1.6 pts
17 April 2026
0%
Context
Own a unit in Enchante By Grid?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Enchante By Grid handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2061. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Enchante By Grid?
- Enchante By Grid was 1.6% built at the site inspection on 11 November 2026. The site has been inspected 2 times since April 2026. The Land Department took 7 site photos at its inspections.
- Is Enchante By Grid delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Enchante By Grid?
- The registered developer is Grid Viv Real Estate Development.
- Which bank holds the escrow account for Enchante By Grid?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.