Enchante By Grid construction progress

The registered completion date for Enchante By Grid is December 2028. At the last site inspection, in November 2026, it was 1.6% built. The developer is Grid Viv Real Estate Development.

1.6%

Built, at the site inspection of 11 November 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
January 2061
Construction started
May 2026
First registered
April 2026
Developer
Grid Viv Real Estate Development
Units
286
Escrow bank
Sharjah Islamic Bank
Name in Arabic
إنشانته باي جريد
Project number
4460
Site inspections
2

Schedule

Between April 2026 and November 2026 the site added about 0.2 points a month. At that rate it would finish around January 2061, more than three months after its registered date of December 2028.

0%25%50%75%100%20272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

11 November 2026

1.6%+1.6 pts

  • Enchante By Grid construction site, inspection photo 1, 11 November 2026
  • Enchante By Grid construction site, inspection photo 2, 11 November 2026
  • Enchante By Grid construction site, inspection photo 3, 11 November 2026
  • Enchante By Grid construction site, inspection photo 4, 11 November 2026

17 April 2026

0%

  • Enchante By Grid construction site, inspection photo 1, 17 April 2026
  • Enchante By Grid construction site, inspection photo 2, 17 April 2026

All 7 site photos, by inspection date

Context

Own a unit in Enchante By Grid?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Enchante By Grid handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around January 2061. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Enchante By Grid?
Enchante By Grid was 1.6% built at the site inspection on 11 November 2026. The site has been inspected 2 times since April 2026. The Land Department took 7 site photos at its inspections.
Is Enchante By Grid delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Enchante By Grid?
The registered developer is Grid Viv Real Estate Development.
Which bank holds the escrow account for Enchante By Grid?
Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.