Empire Gardens construction progress

Empire Gardens is 0% built at the Land Department inspection of July 2026. Developer Empire Gardens Real Estate Development. Completion registered for December 2028.

0%

Built, at the Land Department site inspection of 1 July 2026

Running behind its date

Completion date (Land Department)
December 2028
Finish at recent pace
September 3401
Construction started
April 2026
Registered with the Land Department
January 2026
Developer
Empire Gardens Real Estate Development
Units
221
Escrow bank
Emirates NBD
Name in Arabic
إمباير جاردنز
Land Department project number
4246
Land Department site inspections
2

Schedule

Between December 2025 and July 2026 the site added about 0.0 points a month. At that rate it would finish around September 3401, more than three months after the December 2028 date registered with the Land Department.

0%25%50%75%100%202620272028
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

1 July 2026

0%+0.0 pts

  • Empire Gardens construction site, Land Department inspection photo 1, 1 July 2026
  • Empire Gardens construction site, Land Department inspection photo 2, 1 July 2026
  • Empire Gardens construction site, Land Department inspection photo 3, 1 July 2026
  • Empire Gardens construction site, Land Department inspection photo 4, 1 July 2026

12 December 2025

0%

  • Empire Gardens construction site, Land Department inspection photo 1, 12 December 2025
  • Empire Gardens construction site, Land Department inspection photo 2, 12 December 2025

All 6 site photos, by inspection date

Context

Own a unit in Empire Gardens?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Empire Gardens be completed?
The completion date registered with the Dubai Land Department is December 2028. At the pace of its recent inspections the site would reach 100% around September 3401. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Empire Gardens is built?
0%, measured at the Land Department site inspection on 1 July 2026. The Land Department engineers have inspected the site 2 times since December 2025.
Is Empire Gardens delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Empire Gardens?
The registered developer is Empire Gardens Real Estate Development.
Which bank holds the escrow account for Empire Gardens?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.