Skip to content

Empire Gardens construction progress

The registered completion date for Empire Gardens is December 2028. At the last site inspection, in July 2026, it was 0% built. The developer is Empire Gardens Real Estate Development.

0%

Built, at the site inspection of 1 July 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
September 3401
Construction started
April 2026
First registered
January 2026
Developer
Empire Gardens Real Estate Development
Units
221
Escrow bank
Emirates NBD
Name in Arabic
إمباير جاردنز
Project number
4246
Site inspections
2

Schedule

Between December 2025 and July 2026 the site added about 0.0 points a month. At that rate it would finish around September 3401, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

1 July 2026

0%+0.0 pts

  • Empire Gardens construction site, inspection photo 1, 1 July 2026
  • Empire Gardens construction site, inspection photo 2, 1 July 2026
  • Empire Gardens construction site, inspection photo 3, 1 July 2026
  • Empire Gardens construction site, inspection photo 4, 1 July 2026

12 December 2025

0%

  • Empire Gardens construction site, inspection photo 1, 12 December 2025
  • Empire Gardens construction site, inspection photo 2, 12 December 2025

All 6 site photos, by inspection date

Context

Empire Gardens Real Estate Development has 2 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Empire Gardens?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Empire Gardens handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around September 3401. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Empire Gardens?
Empire Gardens was 0% built at the site inspection on 1 July 2026. The site has been inspected 2 times since December 2025. The Land Department took 6 site photos at its inspections.
Is Empire Gardens delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Empire Gardens?
The registered developer is Empire Gardens Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Empire Gardens?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.