Dar Al Aiham One construction progress
The registered completion date for Dar Al Aiham One is June 2027. At the last site inspection, in November 2026, it was 49% built. The developer is Dar Al Aiham Properties.
49%
Built, at the site inspection of 17 November 2026
Running behind its date
- Registered completion date
- June 2027
- Finish at recent pace
- October 2027
- Construction started
- December 2025
- First registered
- February 2026
- Developer
- Dar Al Aiham Properties
- Units
- 71
- Escrow bank
- United Bank Limited
- Name in Arabic
- دار الأيهم ون
- Project number
- 4323
- Site inspections
- 3
Schedule
Between January 2026 and November 2026 the site added about 4.7 points a month. At that rate it would finish around October 2027, more than three months after its registered date of June 2027.
Site inspections
17 November 2026
49%+28 pts
3 August 2026
21%+21 pts
8 January 2026
0%
Context
Own a unit in Dar Al Aiham One?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Dar Al Aiham One handover date?
- The registered completion date is June 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around October 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Dar Al Aiham One?
- Dar Al Aiham One was 49% built at the site inspection on 17 November 2026. The site has been inspected 3 times since January 2026. The Land Department took 19 site photos at its inspections.
- Is Dar Al Aiham One delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of June 2027.
- Who is building Dar Al Aiham One?
- The registered developer is Dar Al Aiham Properties.
- Which bank holds the escrow account for Dar Al Aiham One?
- United Bank Limited. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.