Damac Islands 2 - Antigua 1 construction progress

Damac Islands 2 - Antigua 1 is 0.3% built at the Land Department inspection of September 2026. Developer Damac Prime Development. Completion registered for December 2030.

0.3%

Built, at the Land Department site inspection of 16 September 2026

Running behind its date

Completion date (Land Department)
December 2030
Finish at recent pace
September 2223
Construction started
July 2026
Registered with the Land Department
March 2026
Units
468
Escrow bank
Mashreq Bank
Name in Arabic
داماك ايلاندز 2 - أنتيجوا 1
Land Department project number
4369
Land Department site inspections
2

Schedule

Between January 2026 and September 2026 the site added about 0.0 points a month. At that rate it would finish around September 2223, more than three months after the December 2030 date registered with the Land Department.

0%25%50%75%100%2027202820292030
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

16 September 2026

0.3%+0.3 pts

  • Damac Islands 2 - Antigua 1 construction site, Land Department inspection photo 1, 16 September 2026
  • Damac Islands 2 - Antigua 1 construction site, Land Department inspection photo 2, 16 September 2026
  • Damac Islands 2 - Antigua 1 construction site, Land Department inspection photo 3, 16 September 2026
  • Damac Islands 2 - Antigua 1 construction site, Land Department inspection photo 4, 16 September 2026

28 January 2026

0%

  • Damac Islands 2 - Antigua 1 construction site, Land Department inspection photo 1, 28 January 2026
  • Damac Islands 2 - Antigua 1 construction site, Land Department inspection photo 2, 28 January 2026

All 8 site photos, by inspection date

Context

Damac Prime Development has 10 projects under construction in Dubai, none past their registered completion dates.

Own a unit in Damac Islands 2 - Antigua 1?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Damac Islands 2 - Antigua 1 be completed?
The completion date registered with the Dubai Land Department is December 2030. At the pace of its recent inspections the site would reach 100% around September 2223. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Damac Islands 2 - Antigua 1 is built?
0.3%, measured at the Land Department site inspection on 16 September 2026. The Land Department engineers have inspected the site 2 times since January 2026.
Is Damac Islands 2 - Antigua 1 delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2030.
Who is building Damac Islands 2 - Antigua 1?
The registered developer is Damac Prime Development. It has 9 other projects under construction in Dubai.
Which bank holds the escrow account for Damac Islands 2 - Antigua 1?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.