Cresswell Plaza construction progress

Cresswell Plaza was registered to complete in September 2026 and is still under construction. At the last site inspection, in November 2026, it was 65% built. The developer is Essa Bokhowa Properties.

65%

Built, at the site inspection of 5 November 2026

2 months past its registered completion date

Registered completion date
September 2026
Finish at recent pace
September 2027
Construction started
April 2025
First registered
January 2026
Developer
Essa Bokhowa Properties
Units
35
Escrow bank
Mashreq Bank
Name in Arabic
كريسويل بلازا
Project number
4359
Site inspections
3

Schedule

Cresswell Plaza was registered to complete in September 2026, 2 months ago, and is still under construction. Over the last year of inspections it has added about 3.3 points a month. Kept at that rate, the site would reach 100% around September 2027.

0%25%50%75%100%2026
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

5 November 2026

65%+4.5 pts

  • Cresswell Plaza construction site, inspection photo 1, 5 November 2026
  • Cresswell Plaza construction site, inspection photo 2, 5 November 2026
  • Cresswell Plaza construction site, inspection photo 3, 5 November 2026
  • Cresswell Plaza construction site, inspection photo 4, 5 November 2026

20 July 2026

60%+26 pts

  • Cresswell Plaza construction site, inspection photo 1, 20 July 2026
  • Cresswell Plaza construction site, inspection photo 2, 20 July 2026
  • Cresswell Plaza construction site, inspection photo 3, 20 July 2026
  • Cresswell Plaza construction site, inspection photo 4, 20 July 2026

27 January 2026

34%

  • Cresswell Plaza construction site, inspection photo 1, 27 January 2026
  • Cresswell Plaza construction site, inspection photo 2, 27 January 2026
  • Cresswell Plaza construction site, inspection photo 3, 27 January 2026
  • Cresswell Plaza construction site, inspection photo 4, 27 January 2026

All 27 site photos, by inspection date

Context

Own a unit in Cresswell Plaza?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Cresswell Plaza handover date?
The registered completion date was September 2026, and the register still lists Cresswell Plaza as under construction. At the pace of its recent inspections the site would reach 100% around September 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Cresswell Plaza?
Cresswell Plaza was 65% built at the site inspection on 5 November 2026. The site has been inspected 3 times since January 2026. The Land Department took 27 site photos at its inspections.
Is Cresswell Plaza delayed?
Yes. Its registered completion date of September 2026 has passed and the project is still listed as under construction.
Who is building Cresswell Plaza?
The registered developer is Essa Bokhowa Properties.
Which bank holds the escrow account for Cresswell Plaza?
Mashreq Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.