Champions Tower2 construction progress

Champions Tower2 is 78% built at the Land Department inspection of March 2017. Developer Fast Solutions Real Estate Development. Completion registered for October 2017.

78%

Built, at the Land Department site inspection of 20 March 2017

107 months past its registered completion date

Completion date (Land Department)
October 2017
Finish at recent pace
September 2021
Construction started
February 2014
Registered with the Land Department
November 2008
Developer
Fast Solutions Real Estate Development
Units
172
Escrow bank
Commercial Bank of Dubai
Name in Arabic
Champions Tower2
Land Department project number
764
Land Department site inspections
5

Schedule

Champions Tower2 was registered to complete in October 2017, 107 months ago, and is still under construction. Over the last year of inspections it has added about 0.4 points a month. Kept at that rate, the site would reach 100% around September 2021.

0%25%50%75%100%201520162017
Progress at each Land Department site inspectionStraight line from start to the Land Department completion date

Site inspections

20 March 2017

78%+5.6 pts

  • Champions Tower2 construction site, Land Department inspection photo 1, 20 March 2017
  • Champions Tower2 construction site, Land Department inspection photo 2, 20 March 2017
  • Champions Tower2 construction site, Land Department inspection photo 3, 20 March 2017
  • Champions Tower2 construction site, Land Department inspection photo 4, 20 March 2017

27 January 2016

73%+12 pts

  • Champions Tower2 construction site, Land Department inspection photo 1, 27 January 2016
  • Champions Tower2 construction site, Land Department inspection photo 2, 27 January 2016
  • Champions Tower2 construction site, Land Department inspection photo 3, 27 January 2016
  • Champions Tower2 construction site, Land Department inspection photo 4, 27 January 2016

25 February 2015

61%+11 pts

  • Champions Tower2 construction site, Land Department inspection photo 1, 25 February 2015
  • Champions Tower2 construction site, Land Department inspection photo 2, 25 February 2015
  • Champions Tower2 construction site, Land Department inspection photo 3, 25 February 2015
  • Champions Tower2 construction site, Land Department inspection photo 4, 25 February 2015

18 October 2014

49%+5.2 pts

  • Champions Tower2 construction site, Land Department inspection photo 1, 18 October 2014
  • Champions Tower2 construction site, Land Department inspection photo 2, 18 October 2014
  • Champions Tower2 construction site, Land Department inspection photo 3, 18 October 2014
  • Champions Tower2 construction site, Land Department inspection photo 4, 18 October 2014

13 April 2014

44%

  • Champions Tower2 construction site, Land Department inspection photo 1, 13 April 2014
  • Champions Tower2 construction site, Land Department inspection photo 2, 13 April 2014
  • Champions Tower2 construction site, Land Department inspection photo 3, 13 April 2014
  • Champions Tower2 construction site, Land Department inspection photo 4, 13 April 2014

All 55 site photos, by inspection date

Context

Own a unit in Champions Tower2?

Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When will Champions Tower2 be completed?
The completion date registered with the Dubai Land Department is October 2017. At the pace of its recent inspections the site would reach 100% around September 2021. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
How much of Champions Tower2 is built?
78%, measured at the Land Department site inspection on 20 March 2017. The Land Department engineers have inspected the site 5 times since April 2014.
Is Champions Tower2 delayed?
Yes. Its registered completion date of October 2017 has passed and the Land Department still lists it as under construction.
Who is building Champions Tower2?
The registered developer is Fast Solutions Real Estate Development.
Which bank holds the escrow account for Champions Tower2?
Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.