Champions Tower2 construction progress
Champions Tower2 was registered to complete in October 2017 and is still under construction. At the last site inspection, in March 2017, it was 78% built. The developer is Fast Solutions Real Estate Development.
78%
Built, at the site inspection of 20 March 2017
109 months past its registered completion date
- Registered completion date
- October 2017
- Finish at recent pace
- September 2021
- Construction started
- February 2014
- First registered
- November 2008
- Developer
- Fast Solutions Real Estate Development
- Units
- 172
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- Champions Tower2
- Project number
- 764
- Site inspections
- 5
Schedule
Champions Tower2 was registered to complete in October 2017, 109 months ago, and is still under construction. Over the last year of inspections it has added about 0.4 points a month. Kept at that rate, the site would reach 100% around September 2021.
Site inspections
20 March 2017
78%+5.6 pts
27 January 2016
73%+12 pts
25 February 2015
61%+11 pts
18 October 2014
49%+5.2 pts
13 April 2014
44%
Context
Fast Solutions Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.
Own a unit in Champions Tower2?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Champions Tower2 handover date?
- The registered completion date was October 2017, and the register still lists Champions Tower2 as under construction. At the pace of its recent inspections the site would reach 100% around September 2021. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Champions Tower2?
- Champions Tower2 was 78% built at the site inspection on 20 March 2017. The site has been inspected 5 times since April 2014. The Land Department took 55 site photos at its inspections.
- Is Champions Tower2 delayed?
- Yes. Its registered completion date of October 2017 has passed and the project is still listed as under construction.
- Who is building Champions Tower2?
- The registered developer is Fast Solutions Real Estate Development. It has 1 other project under construction in Dubai.
- Which bank holds the escrow account for Champions Tower2?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
- Champion Tower 3Also by Fast Solutions Real Estate Development. 95%, Due September 2028.
- Checking an off-plan project's progressHow to read the completion percentage and what escrow allows when a payment runs ahead.
- Off-plan handover in DubaiWhat happens between 100% and getting your keys.
- Snagging a new Dubai homeHow to inspect the unit before you accept it.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.