Champions Tower2 construction progress
Champions Tower2 is 78% built at the Land Department inspection of March 2017. Developer Fast Solutions Real Estate Development. Completion registered for October 2017.
78%
Built, at the Land Department site inspection of 20 March 2017
107 months past its registered completion date
- Completion date (Land Department)
- October 2017
- Finish at recent pace
- September 2021
- Construction started
- February 2014
- Registered with the Land Department
- November 2008
- Developer
- Fast Solutions Real Estate Development
- Units
- 172
- Escrow bank
- Commercial Bank of Dubai
- Name in Arabic
- Champions Tower2
- Land Department project number
- 764
- Land Department site inspections
- 5
Schedule
Champions Tower2 was registered to complete in October 2017, 107 months ago, and is still under construction. Over the last year of inspections it has added about 0.4 points a month. Kept at that rate, the site would reach 100% around September 2021.
Site inspections
20 March 2017
78%+5.6 pts
27 January 2016
73%+12 pts
25 February 2015
61%+11 pts
18 October 2014
49%+5.2 pts
13 April 2014
44%
Context
Own a unit in Champions Tower2?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Champions Tower2 be completed?
- The completion date registered with the Dubai Land Department is October 2017. At the pace of its recent inspections the site would reach 100% around September 2021. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Champions Tower2 is built?
- 78%, measured at the Land Department site inspection on 20 March 2017. The Land Department engineers have inspected the site 5 times since April 2014.
- Is Champions Tower2 delayed?
- Yes. Its registered completion date of October 2017 has passed and the Land Department still lists it as under construction.
- Who is building Champions Tower2?
- The registered developer is Fast Solutions Real Estate Development.
- Which bank holds the escrow account for Champions Tower2?
- Commercial Bank of Dubai. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.