Champions Tower2 construction progress

Champions Tower2 was registered to complete in October 2017 and is still under construction. At the last site inspection, in March 2017, it was 78% built. The developer is Fast Solutions Real Estate Development.

78%

Built, at the site inspection of 20 March 2017

109 months past its registered completion date

Registered completion date
October 2017
Finish at recent pace
September 2021
Construction started
February 2014
First registered
November 2008
Developer
Fast Solutions Real Estate Development
Units
172
Escrow bank
Abu Dhabi Commercial Bank
Name in Arabic
Champions Tower2
Project number
764
Site inspections
5

Schedule

Champions Tower2 was registered to complete in October 2017, 109 months ago, and is still under construction. Over the last year of inspections it has added about 0.4 points a month. Kept at that rate, the site would reach 100% around September 2021.

0%25%50%75%100%201520162017
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

20 March 2017

78%+5.6 pts

  • Champions Tower2 construction site, inspection photo 1, 20 March 2017
  • Champions Tower2 construction site, inspection photo 2, 20 March 2017
  • Champions Tower2 construction site, inspection photo 3, 20 March 2017
  • Champions Tower2 construction site, inspection photo 4, 20 March 2017

27 January 2016

73%+12 pts

  • Champions Tower2 construction site, inspection photo 1, 27 January 2016
  • Champions Tower2 construction site, inspection photo 2, 27 January 2016
  • Champions Tower2 construction site, inspection photo 3, 27 January 2016
  • Champions Tower2 construction site, inspection photo 4, 27 January 2016

25 February 2015

61%+11 pts

  • Champions Tower2 construction site, inspection photo 1, 25 February 2015
  • Champions Tower2 construction site, inspection photo 2, 25 February 2015
  • Champions Tower2 construction site, inspection photo 3, 25 February 2015
  • Champions Tower2 construction site, inspection photo 4, 25 February 2015

18 October 2014

49%+5.2 pts

  • Champions Tower2 construction site, inspection photo 1, 18 October 2014
  • Champions Tower2 construction site, inspection photo 2, 18 October 2014
  • Champions Tower2 construction site, inspection photo 3, 18 October 2014
  • Champions Tower2 construction site, inspection photo 4, 18 October 2014

13 April 2014

44%

  • Champions Tower2 construction site, inspection photo 1, 13 April 2014
  • Champions Tower2 construction site, inspection photo 2, 13 April 2014
  • Champions Tower2 construction site, inspection photo 3, 13 April 2014
  • Champions Tower2 construction site, inspection photo 4, 13 April 2014

All 55 site photos, by inspection date

Context

Fast Solutions Real Estate Development has 2 projects under construction in Dubai; 1 has passed its registered completion date.

Own a unit in Champions Tower2?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Champions Tower2 handover date?
The registered completion date was October 2017, and the register still lists Champions Tower2 as under construction. At the pace of its recent inspections the site would reach 100% around September 2021. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Champions Tower2?
Champions Tower2 was 78% built at the site inspection on 20 March 2017. The site has been inspected 5 times since April 2014. The Land Department took 55 site photos at its inspections.
Is Champions Tower2 delayed?
Yes. Its registered completion date of October 2017 has passed and the project is still listed as under construction.
Who is building Champions Tower2?
The registered developer is Fast Solutions Real Estate Development. It has 1 other project under construction in Dubai.
Which bank holds the escrow account for Champions Tower2?
Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.