Celia Homes construction progress

The registered completion date for Celia Homes is November 2027. At the last site inspection, in November 2026, it was 41% built. The developer is Abou Eid Real Estate Development.

41%

Built, at the site inspection of 10 November 2026

On pace for its date

Registered completion date
November 2027
Finish at recent pace
December 2027
Construction started
November 2025
First registered
December 2025
Developer
Abou Eid Real Estate Development
Units
207
Escrow bank
Emirates NBD
Name in Arabic
سيليا هومز
Project number
4170
Site inspections
3

Schedule

Since June 2026 Celia Homes has added about 4.5 points a month. That puts 100% around December 2027, within three months of its registered completion date of November 2027.

0%25%50%75%100%20262027
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

10 November 2026

41%+21 pts

  • Celia Homes construction site, inspection photo 1, 10 November 2026
  • Celia Homes construction site, inspection photo 2, 10 November 2026
  • Celia Homes construction site, inspection photo 3, 10 November 2026
  • Celia Homes construction site, inspection photo 4, 10 November 2026

22 June 2026

20%+20 pts

  • Celia Homes construction site, inspection photo 1, 22 June 2026
  • Celia Homes construction site, inspection photo 2, 22 June 2026
  • Celia Homes construction site, inspection photo 3, 22 June 2026
  • Celia Homes construction site, inspection photo 4, 22 June 2026

29 October 2025

0%

  • Celia Homes construction site, inspection photo 1, 29 October 2025
  • Celia Homes construction site, inspection photo 2, 29 October 2025

All 19 site photos, by inspection date

Context

Own a unit in Celia Homes?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Celia Homes handover date?
The registered completion date is November 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around December 2027. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Celia Homes?
Celia Homes was 41% built at the site inspection on 10 November 2026. The site has been inspected 3 times since October 2025. The Land Department took 19 site photos at its inspections.
Is Celia Homes delayed?
Not on current figures. At the rate of the last year it finishes within three months of its registered date of November 2027.
Who is building Celia Homes?
The registered developer is Abou Eid Real Estate Development.
Which bank holds the escrow account for Celia Homes?
Emirates NBD. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.