Skip to content

Barari Palace construction progress

The registered completion date for Barari Palace is December 2028. At the last site inspection, in June 2026, it was 0% built. The developer is Ary & Maz Development.

0%

Built, at the site inspection of 22 June 2026

Running behind its date

Registered completion date
December 2028
Finish at recent pace
November 3654
Construction started
December 2025
First registered
December 2025
Developer
Ary & Maz Development
Units
225
Escrow bank
Emirates Islamic Bank
Name in Arabic
براري بالاس
Project number
4164
Site inspections
2

Schedule

Between October 2025 and June 2026 the site added about 0.0 points a month. At that rate it would finish around November 3654, more than three months after its registered date of December 2028.

0%25%50%75%100%202620272028
Progress at each site inspectionStraight line from start to the registered completion date

Site inspections

22 June 2026

0%+0.0 pts

  • Barari Palace construction site, inspection photo 1, 22 June 2026
  • Barari Palace construction site, inspection photo 2, 22 June 2026
  • Barari Palace construction site, inspection photo 3, 22 June 2026
  • Barari Palace construction site, inspection photo 4, 22 June 2026

27 October 2025

0%

  • Barari Palace construction site, inspection photo 1, 27 October 2025
  • Barari Palace construction site, inspection photo 2, 27 October 2025

All 7 site photos, by inspection date

Context

Own a unit in Barari Palace?

Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.

Notify me when it launches

Questions

When is the Barari Palace handover date?
The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around November 3654. RERA asks developers to update their dates as projects move, so check the register before relying on it.
What is the latest construction update on Barari Palace?
Barari Palace was 0% built at the site inspection on 22 June 2026. The site has been inspected 2 times since October 2025. The Land Department took 7 site photos at its inspections.
Is Barari Palace delayed?
It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
Who is building Barari Palace?
The registered developer is Ary & Maz Development.
Which bank holds the escrow account for Barari Palace?
Emirates Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.

Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.