Art House Hills By Adaan And Tuscany construction progress
The registered completion date for Art House Hills By Adaan And Tuscany is December 2028. At the last site inspection, in September 2026, it was 0.2% built. The developer is Art House Hills Residences Development.
0.2%
Built, at the site inspection of 29 September 2026
Running behind its date
- Registered completion date
- December 2028
- Finish at recent pace
- February 2457
- Construction started
- February 2026
- First registered
- January 2026
- Developer
- Art House Hills Residences Development
- Units
- 328
- Escrow bank
- Sharjah Islamic Bank
- Name in Arabic
- آرت هاوس هيلز من قبل آدان و توسكاني
- Project number
- 4235
- Site inspections
- 3
Schedule
Between November 2025 and September 2026 the site added about 0.0 points a month. At that rate it would finish around February 2457, more than three months after its registered date of December 2028.
Site inspections
29 September 2026
0.2%+0.2 pts
10 June 2026
0%+0.0 pts
18 November 2025
0%
Context
Own a unit in Art House Hills By Adaan And Tuscany?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Art House Hills By Adaan And Tuscany handover date?
- The registered completion date is December 2028. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around February 2457. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Art House Hills By Adaan And Tuscany?
- Art House Hills By Adaan And Tuscany was 0.2% built at the site inspection on 29 September 2026. The site has been inspected 3 times since November 2025. The Land Department took 10 site photos at its inspections.
- Is Art House Hills By Adaan And Tuscany delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of December 2028.
- Who is building Art House Hills By Adaan And Tuscany?
- The registered developer is Art House Hills Residences Development.
- Which bank holds the escrow account for Art House Hills By Adaan And Tuscany?
- Sharjah Islamic Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.