Ahs Tower construction progress
Ahs Tower is 67% built at the Land Department inspection of May 2026. Developer Ahs Tower Holding Development S.o.c. Completion registered for January 2027.
67%
Built, at the Land Department site inspection of 19 May 2026
Running behind its date
- Completion date (Land Department)
- January 2027
- Finish at recent pace
- April 2028
- Construction started
- October 2025
- Registered with the Land Department
- December 2025
- Developer
- Ahs Tower Holding Development S.o.c
- Units
- 83
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ايه اتش اس تاور
- Land Department project number
- 4245
- Land Department site inspections
- 2
Schedule
Between December 2025 and May 2026 the site added about 1.4 points a month. At that rate it would finish around April 2028, more than three months after the January 2027 date registered with the Land Department.
Site inspections
19 May 2026
67%+7.3 pts
11 December 2025
60%
Context
Own a unit in Ahs Tower?
Mulki follows this project for you: each new Land Department inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When will Ahs Tower be completed?
- The completion date registered with the Dubai Land Department is January 2027. At the pace of its recent inspections the site would reach 100% around April 2028. Developers can apply to the Land Department to extend the date, so check the register before relying on it.
- How much of Ahs Tower is built?
- 67%, measured at the Land Department site inspection on 19 May 2026. The Land Department engineers have inspected the site 2 times since December 2025.
- Is Ahs Tower delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
- Who is building Ahs Tower?
- The registered developer is Ahs Tower Holding Development S.o.c.
- Which bank holds the escrow account for Ahs Tower?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of Land Department inspections, not a forecast from the developer. Site photos belong to the Dubai Land Department. See how Mulki works with Land Department data.