Ahs Tower construction progress
The registered completion date for Ahs Tower is January 2027. At the last site inspection, in May 2026, it was 67% built. The developer is Ahs Tower Holding Development S.o.c.
67%
Built, at the site inspection of 19 May 2026
Running behind its date
- Registered completion date
- January 2027
- Finish at recent pace
- April 2028
- Construction started
- October 2025
- First registered
- December 2025
- Developer
- Ahs Tower Holding Development S.o.c
- Units
- 83
- Escrow bank
- Abu Dhabi Commercial Bank
- Name in Arabic
- ايه اتش اس تاور
- Project number
- 4245
- Site inspections
- 2
Schedule
Between December 2025 and May 2026 the site added about 1.4 points a month. At that rate it would finish around April 2028, more than three months after its registered date of January 2027.
Site inspections
19 May 2026
67%+7.3 pts
11 December 2025
60%
Context
Own a unit in Ahs Tower?
Mulki follows this project for you: each new site inspection, your payment plan, the handover date and what the unit is worth today, in one private app.
Notify me when it launchesQuestions
- When is the Ahs Tower handover date?
- The registered completion date is January 2027. Handover of units starts once construction is complete, on the developer's schedule. At the pace of its recent inspections the site would reach 100% around April 2028. RERA asks developers to update their dates as projects move, so check the register before relying on it.
- What is the latest construction update on Ahs Tower?
- Ahs Tower was 67% built at the site inspection on 19 May 2026. The site has been inspected 2 times since December 2025. The Land Department took 13 site photos at its inspections.
- Is Ahs Tower delayed?
- It is running behind. At the rate of the last year it would finish more than three months after its registered date of January 2027.
- Who is building Ahs Tower?
- The registered developer is Ahs Tower Holding Development S.o.c.
- Which bank holds the escrow account for Ahs Tower?
- Abu Dhabi Commercial Bank. Dubai law requires payments for off-plan units to go into a project escrow account at a bank approved by the Land Department, so buyer money is held against this project only.
Progress, dates, developer, units and escrow bank come from the Dubai Land Department’s Mashrooi register, read daily. The pace and the projected finish are Mulki’s own arithmetic on the last year of inspections, not a forecast from the developer. The site photos are the Land Department’s own. See how Mulki works with Land Department data.