89 photos from 10 site inspections, newest first. The percentage is how much of Urbana was built on the day of each visit.

26 March 2020100% built

30 December 201998% built

21 August 201997% built

22 April 201990% built

7 March 201987% built

9 September 201864% built

1 May 201844% built

11 February 201825% built

14 November 201713% built

24 July 20175.4% built

Back to Urbana construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.