Parkside construction photos

99 photos from 10 site inspections, newest first. The percentage is how much of Parkside was built on the day of each visit.

18 April 2022100% built

29 November 202190% built

8 August 202180% built

18 April 202164% built

21 December 202051% built

18 August 202040% built

14 April 202031% built

13 January 202018% built

25 August 20192.6% built

2 May 20190.8% built

Back to Parkside construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.