Greenview 3 construction photos

50 photos from 8 site inspections, newest first. The percentage is how much of Greenview 3 was built on the day of each visit.

10 February 2025100% built

7 January 202593% built

18 August 202465% built

25 March 202430% built

28 September 20236.4% built

1 June 20232.0% built

20 February 20231.3% built

9 November 20220.5% built

Back to Greenview 3 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.