Canal Front Residences-Cf5&Cf6 construction photos

82 photos from 9 site inspections, newest first. The percentage is how much of Canal Front Residences-Cf5&Cf6 was built on the day of each visit.

8 November 2024100% built

4 June 202499% built

4 March 202498% built

24 August 202363% built

18 May 202350% built

2 February 202340% built

10 November 202236% built

3 August 202233% built

21 February 202233% built

Back to Canal Front Residences-Cf5&Cf6 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.