Canal Front Residences-Cf3&Cf4 construction photos

73 photos from 8 site inspections, newest first. The percentage is how much of Canal Front Residences-Cf3&Cf4 was built on the day of each visit.

18 March 2024100% built

6 December 202392% built

24 August 202381% built

18 May 202366% built

2 February 202351% built

10 November 202241% built

3 August 202231% built

14 December 202131% built

Back to Canal Front Residences-Cf3&Cf4 construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.