Divine Residencia construction photos
55 photos from 6 site inspections, newest first. The percentage is how much of Divine Residencia was built on the day of each visit.
13 April 2026100% built
28 January 202696% built
10 October 202573% built
9 April 202550% built
23 October 202417% built
20 December 20230% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.