64 photos from 8 site inspections, newest first. The percentage is how much of Uniestate Sports Tower was built on the day of each visit.

27 April 2017100% built

29 November 201697% built

15 August 201685% built

25 April 201664% built

12 January 201655% built

13 August 201541% built

26 March 201534% built

22 December 201427% built

Back to Uniestate Sports Tower construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.