Stadium Point construction photos

91 photos from 11 site inspections, newest first. The percentage is how much of Stadium Point was built on the day of each visit.

24 May 201582% built

8 February 201562% built

16 December 201457% built

19 October 201450% built

19 August 201432% built

2 July 201428% built

26 May 201424% built

31 March 201420% built

18 December 201316% built

22 May 201316% built

16 September 201218% built

Back to Stadium Point construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.