Sportz By Danube construction photos

81 photos taken by Dubai Land Department engineers at 10 site inspections, newest first. The percentage is how much of Sportz By Danube was built on the day of each visit.

7 September 202669% built

12 May 202664% built

17 March 202655% built

25 February 202653% built

9 December 202547% built

1 September 202533% built

30 May 202521% built

9 January 202512% built

12 April 20240.2% built

14 November 20230% built

Back to Sportz By Danube construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.