Profile Residence construction photos

174 photos from 21 site inspections, newest first. The percentage is how much of Profile Residence was built on the day of each visit.

1 April 2024100% built

25 September 202392% built

21 June 202381% built

1 March 202370% built

10 November 202265% built

22 July 202262% built

12 September 202161% built

24 March 202162% built

8 July 201962% built

18 March 201962% built

6 December 201762% built

22 February 201761% built

15 August 201660% built

9 May 201655% built

20 January 201652% built

21 September 201543% built

25 May 201534% built

29 January 201525% built

19 August 201417% built

6 May 201415% built

27 January 201415% built

Back to Profile Residence construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.