Olympic Park 6 construction photos
97 photos from 10 site inspections, newest first. The percentage is how much of Olympic Park 6 was built on the day of each visit.
28 February 2019100% built
21 June 201797% built
5 September 201695% built
6 May 201590% built
25 January 201577% built
16 October 201465% built
10 July 201451% built
27 March 201444% built
2 January 201430% built
24 July 201317% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.