Oasis Tower One construction photos

99 photos from 10 site inspections, newest first. The percentage is how much of Oasis Tower One was built on the day of each visit.

14 May 2020100% built

30 July 201997% built

25 April 201895% built

28 November 201792% built

5 July 201790% built

28 February 201785% built

24 October 201681% built

6 April 201675% built

10 September 201572% built

21 September 201450% built

Back to Oasis Tower One construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.