Global Golf Residence 2 construction photos
166 photos from 18 site inspections, newest first. The percentage is how much of Global Golf Residence 2 was built on the day of each visit.
16 January 2020100% built
17 April 201994% built
27 December 201889% built
30 September 201886% built
30 May 201884% built
12 February 201881% built
22 October 201775% built
5 July 201771% built
7 March 201766% built
27 November 201661% built
7 August 201655% built
4 April 201650% built
22 December 201545% built
26 August 201540% built
10 March 201533% built
29 October 201427% built
15 September 201423% built
15 May 201420% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.