The Pulse Residence construction photos
44 photos from 5 site inspections, newest first. The percentage is how much of The Pulse Residence was built on the day of each visit.
16 February 2020100% built
7 July 201965% built
6 December 201841% built
15 May 201816% built
27 December 20173.0% built
All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.