The Pulse Residence Icon construction photos

55 photos from 6 site inspections, newest first. The percentage is how much of The Pulse Residence Icon was built on the day of each visit.

3 November 2020100% built

4 February 202071% built

25 September 201952% built

2 April 201928% built

15 May 20185.0% built

27 December 20171.0% built

Back to The Pulse Residence Icon construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.