South Bay 6 Premium construction photos

24 photos taken by Dubai Land Department engineers at 4 site inspections, newest first. The percentage is how much of South Bay 6 Premium was built on the day of each visit.

23 July 202682% built

11 February 202645% built

6 May 202517% built

13 May 20240% built

Back to South Bay 6 Premium construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.