Mag 5 Boulevard construction photos

137 photos from 14 site inspections, newest first. The percentage is how much of Mag 5 Boulevard was built on the day of each visit.

6 February 2020100% built

19 November 201992% built

25 August 201984% built

9 January 201967% built

15 November 201865% built

31 October 201864% built

16 September 201862% built

9 May 201852% built

17 December 201730% built

30 October 201725% built

30 July 201731% built

19 February 201711% built

25 December 20162.0% built

16 October 20160.3% built

Back to Mag 5 Boulevard construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.