127 photos from 14 site inspections, newest first. The percentage is how much of Celestia was built on the day of each visit.

7 August 2019100% built

18 October 201898% built

3 June 201895% built

31 January 201892% built

24 October 201788% built

10 August 201784% built

11 May 201776% built

27 December 201661% built

28 August 201646% built

26 April 201633% built

22 December 201520% built

24 August 201512% built

13 April 20156.1% built

14 December 20145.5% built

Back to Celestia construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.