Opalz By Danube construction photos

48 photos from 8 site inspections, newest first. The percentage is how much of Opalz By Danube was built on the day of each visit.

24 April 2025100% built

26 March 202597% built

27 November 202483% built

23 April 202428% built

13 December 202320% built

24 August 202310% built

1 May 20231.9% built

21 September 20220% built

Back to Opalz By Danube construction progress

All photos belong to the Dubai Land Department and were taken during its Mashrooi escrow inspections. Mulki shows them as published, with the inspection date and recorded completion each was taken at.